CPM solution Activity Duration ET LT TF Training 6 initial activity 0 LT(3) = 26-8=18 LT(4) = 16-7=9 9 9-0-6 3 Purchasing 9 initial activity 0 LT(3) = 26-8=18 LT(4) = 16-7=9 9 9-0-9 0 Production 8 ET(1) = 0+6=6 ET(2) = 0+9=9 9 LT(6) = 38-12=26 26 26-9-8 9 Quality control 7 ET(1) = 0+6=6 ET(2) = 0+9=9 9 LT(5) = 26-10=16 16 16-9-7 0 Assembling 10 ET(4) = 9+7=16 16 LT(6) = 38-12=26 26 26-16-10 0 Transporting 12 ET(3) = 8+9=17 ET(5) = 16+10=26 26 terminal activity 38 38-26-12 0 Critical path: Purchasing → Quality control → Assembling → Transporting